Preparatory work
Completed
Foundation pit / Excavation
Completed
Foundation
Completed
Framework / Frame
17/17
Walls
17/17
Roofing / Roof
Completed
Glazing
Completed
Facade
Completed
Engineering systems
In progress
Finishing / Decoration
Completed
Landscaping / Site improvement
In progress
Commissioning
In progress
This page shows construction progress by section for Times Current section: 1 Handover: 12.2026
Quick construction summary
Readiness: 79%
Sections and work stages
- 1 - Engineering systems