Preparatory work
Completed
Foundation pit / Excavation
Completed
Foundation
In progress
Framework / Frame
Not started
Walls
Not started
Roofing / Roof
Not started
Glazing
Not started
Facade
Not started
Engineering systems
Not started
Finishing / Decoration
Not started
Landscaping / Site improvement
Not started
Commissioning
Not started
This page shows construction progress by section for Quarter SOHO Current section: A Handover: 12.2028
Quick construction summary
Readiness: 21%
Sections and work stages
- A - Foundation
- B - Foundation