Prostanstvo (Dachnaya) • Construction progress

Floors: 8. Delivery: 06.2026

Floors: 8. Delivery: 06.2026

Floors: 6. Delivery: 10.2025

Floors: 6. Delivery: 10.2024

Floors: 6. Delivery: 10.2024

Floors: 5. Delivery: 05.2024

Preparatory work
Completed
Foundation pit / Excavation
Completed
Foundation
Completed
Framework / Frame
8/8
Walls
8/8
Roofing / Roof
Completed
Glazing
Completed
Facade
In progress
Engineering systems
In progress
Finishing / Decoration
In progress
Landscaping / Site improvement
In progress
Commissioning
Not started

This page shows construction progress by section for Prostanstvo (Dachnaya) Current section: Б Handover: 06.2026

Quick construction summary

Readiness: 67-100%

Sections and work stages

  • Б - Facade
  • В - Facade
  • А - Engineering systems
  • Д - Commissioning
  • Г - Engineering systems
  • Е - Commissioning